Miller Avenue Improvements Project

​​​​​​​​​

header image
Skip Navigation LinksHome » Departments » Engineering » Miller Avenue Improvements Project

Project limits

Phase 1: Chapin Street to Newport Road​                                                                                  Miller Improvements map image.jpg

  • Water Main Replacement
  • Storm Sewer Improvements
  • Road Repaving

Phase 2: First Street to Maple Roa​d

  • ​​​Combine separate bike lanes into a single two-way cycle track
  • Install speed management devices

Staff have produced a video​ (YouTube) that provides a detailed overview of the project. 

Project Manager
‍Jane Allen, P.E.
[email protected]     
734.794.6​410 x43678

                     For updates on the project

                   ​  Subscribe fo​r Notifications

Timeline

Design & Public Engagement

Fall/Winter 2023

Obtain Construction Bids
Jan/Feb. 2024
Construction

Begins late Spring 2024​

​Why is this project being done?

  • Water mains have been identified for replacement due to age and condition of existing infrastructure.

  • Funding for improvements within the Allen Creek watershed have been allocated for underground detention of rain runoff within the project area.

  • The road condition from Newport to Chapin warrants repaving. This section of pavement was not repaved during the 2013 Miller reconstruction work.

  • Miller Avenue is an all ages and abilities bike corridor, with funding available to upgrade the bike facilities. ​​

Potential impacts to residents​

  • Residents in the vicinity will experience noise and dust normally associated with construction.

  • Thru traffic will be detoured around the construction zone.

  • Local access for residents on Miller Avenue will be maintained.


Cost & Funding Source

This project is being funded by multiple sources, including City Water Utility and Stormwater Utility Funds, State Transportation funds, County Road Millage Funds, and American Rescue Plan Act (ARPA) funds.