Fernwood Avenue (Packard - Lorraine) – Process Completed; Installed November 2021; one raised intersection, two speed tables, one raised crosswalk, and one median island.
Feedback was obtained pertaining to the devices installed one year after installation. The summary can be found here: Feedback Survey Summary (PDF).

Project materials:
- Qualification Criteria Matrix (PDF) Updated - March 2020
- Initial Questionnaire Summary (PDF) Updated - Jan 2020
- Save-the-Date Postcard (PDF) Update - Jan 2020
- Meeting #1 Powerpoint (PDF) Updated - March 2020
- Meeting #2 Guided Tour and Virtual Materials (PDF) - May 2020
- Preliminary Plan (PDF) - May 2020
- Meeting #2 Powerpoint (PDF) - Updated June 2020
- Final Plan (PDF) - June 2020
- Final Poll Letter and Results (PDF) - August 2020
- Feedback Survey Summary (PDF) - March 2022