Independence Boulevard Sidewalk Gap

​​

header image
Skip Navigation LinksHome » Departments » Engineering » Independence Boulevard Sidewalk Gap

Project Manager: 

Andrea Wright
[email protected]
734.794.6410 ext. 43674




Project limits

South side of Independence Boulevard from Victoria to Essex.


Timeline

  • September-October 2024: Surv​ey and Preliminary Design
  • November 2024: Public Input
  • December 2024: Finalize Design
  • January 2025: Bid Project
  • Summer-Fall 2025: Construction, in coordination with the Annual Resurfacing Program​

Why is this project being done?

Filling gaps in the sidewalk system is consistent with both Ann Arbor's Moving Together Towards Vision Zero transportation plan and Complete Streets Policy. Providing sidewalks where they currently do not exist can:

  • Improve safety for people of all ages and abilities
  • Encourage active transportation and community health
  • Provide a continuous human experience
  • Provide more transportation options
  • Eliminate the practice of walking along the road and across traffic

In November of 2020, voters approved a six-year New Sidewalk Millage. This millage, which will generate an annual revenue of approximately $1.3 million, will be used exclusively for sidewalk gap filling projects. Funding from the New Sidewalk Millage applies to all sidewalks constructed adjacent to tax-paying parcels in the City of Ann Arbor.  

The city developed a prioritization system for the public right-of-way where sidewalks do not currently exist. The system considers proximity to schools, transit, and other pedestrian attractors; equity; classification of adjacent road; community support/citizen requests; and safety. This system identifies the highest priority sidewalk gaps for inclusion in the City's Capital Improvements Plan (CIP).  Please visit the city's new sidewalk we​bsite  for more information and to view the dashboard.​

Work to be done

New sidewalk will be installed along the south side of Independence Boulevard from Victoria to Essex.


Possible impacts during work​

Staff will take into consideration the following while designing the new sidewalk within the right-of-way, the considerations are:

  • Removing and/or saving trees

  • Existing utilities, fences, landscaping, and drainage

During the design and public input process, staff will reach out to individual property owners adjacent to the project to discuss project details and impacts.

 

Costs and funding source

Sidewalk Construction Millage​​