Project Overview
Utility improvements are being made to increase the city's sewer system capacity.
Project Limits
The project will take place in the areas of First Street from West Washington Street to Miller Avenue and along West Washington Street from Third Street to First Street. This route was selected due to environmental factors, right-of-way access and scheduling needs.
Timeline
- Planning & Design: January 2024 – July 2025
- Construction: December 2025 – August 2026
Why is this project begin done?
To support future development and population growth, the City of Ann Arbor and the University of Michigan are partnering to expand the city's sewer system capacity.
The project aligns with the City of Ann Arbor's Master Plan, which outlines the need for future capacity enhancements, but also accommodates the University of Michigan's plans to develop a new Central Campus residential complex that will be built and occupied by Fall 2026.
Potential construction impacts
- Noise and dust from construction work
- Road and sidewalk closures
- Parking restrictions
Trenchless installation methods will be used throughout construction to reduce surface impacts and to expedite the project's completion schedule.
Funding source
The University of Michigan is partnering with the City by providing funding for this project.